Watch It Being Done
5 videos, 117 minutes in total. Every one carries a transcript — which is not a nicety, it is the only way a video becomes something Scout can answer from.
All videos
Direct Connection: Street Lighting, LV and Telecoms
Setting up and earthing the Genny4, connecting at a lighting column, what to do when the column is concrete, gas risers, and the approvals you need before a telecoms lid comes up.
Watch 6:06 VideoLocating HV Cables with a Genny and CAT
Techniques and the things that make HV harder than LV: where you can and cannot get a connection, what the signal does on a bonded network, and how to read what comes back.
Watch 12:40 VideoGetting the Best Out of Your Genny and CAT
The full webinar. Signal application from first principles: why you start with street lighting, the two ways lighting is wired, dual frequency, earthing the transmitter, induction against direct connection, and where the signal actually goes once you have applied it.
Watch 1:12:19 VideoThe Genny First Approach Explained
Why the signal generator goes on before anything else, and what a passive-only sweep is actually telling you. The training video behind the method.
Watch 16:07 VideoGenny and CAT Training: The Full Run-Through
The whole method end to end in under ten minutes — pre-use checks, applying a signal, locating, pinpointing and taking a depth reading.
Watch 9:40